As of January 31, 2010
|
|
Budget |
Expenditures |
Remaining |
% Spent |
|
Construction Progress |
| 2004 Bond Package |
| Proposition One |
|
|
|
|
|
|
|
| High School Renovations/Additions |
* |
$45,179,015 |
$45,179,015 |
$- |
100.00% |
|
Complete |
|
|
|
|
|
|
|
|
| WGMS Phase II |
|
$12,457,732 |
$12,457,732 |
$- |
100.00% |
|
Complete |
|
|
|
|
|
|
|
|
| Capital Improvements |
|
$4,119,378 |
$3,867,344 |
$252,034 |
93.88% |
|
The remaining balance is for the emergency vehicle
access road that has not been completed at Longbranch due to delays from the
developer for the property behind the school. The district will begin work
when the street to connect the two is cut. A temporary drop off lane has
been constructed to keep overflow on FM 1387 to a minimum. |
|
|
|
|
|
|
|
|
| Technology |
|
$1,900,000 |
$1,900,000 |
$- |
100.00% |
|
Complete |
|
|
|
|
|
|
|
|
| School Buses |
|
$520,000 |
$520,000 |
$- |
100.00% |
|
Complete |
|
|
|
|
|
|
|
|
| Total Proposition One |
|
$64,176,125 |
$63,924,091 |
$252,034 |
99.61% |
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
| Proposition Two |
|
|
|
|
|
|
|
| Multi-purpose Stadium |
* |
$15,013,248 |
$15,013,248 |
$- |
100.00% |
|
Complete |
| |
|
|
|
|
|
|
|
| Proposition Three |
|
|
|
|
|
|
|
| Land |
|
$3,800,000 |
$2,404,620 |
$1,395,380 |
63.28% |
|
High School #2 property purchased |
| |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
| May 2006 Bond Package |
| LaRue Miller Elementary |
|
$17,157,216 |
$16,088,862 |
$1,068,354 |
93.77% |
|
Complete |
|
|
|
|
|
|
|
|
| Baxter & FSMS Renovations/Additions |
* |
$13,369,837 |
$12,860,073 |
$509,764 |
96.19% |
|
Complete |
|
|
|
|
|
|
|
|
| Capital Improvements |
|
$3,417,229 |
$3,008,601 |
$408,628 |
88.04% |
|
Some technology upgrades such as WAN are yet to be
completed. |
|
|
|
|
|
|
|
|
| Instructional Technology |
* |
$1,668,874 |
$1,563,346 |
$105,528 |
93.68% |
|
New teacher workstations, wireless rolling labs and
multi media presentation stations have been purchased; network upgrades,
e-instruction devices and security cameras at all campuses are yet to be
completed. |
|
|
|
|
|
|
|
|
| School Buses |
* |
$316,106 |
$316,106 |
$- |
100.00% |
|
Complete |
|
|
|
|
|
|
|
|
| Total |
|
$35,929,262 |
$33,836,988 |
$2,092,274 |
94.18% |
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
| November 2007 Bond Package |
| Ag Facility |
|
$2,500,000 |
$2,362,496 |
$137,504 |
94.50% |
|
Building phase complete. |
* Includes approved and pending allocated
interest |
|
|
| |
| Top |
| |
| |
|
| |
MISD School
Bond History |
| Updated: 10/30/09 |
| |
| Election Date |
Amount |
Props |
Purpose |
Voted For |
Voted Against |
Total Votes |
Results |
| Nov.
6, 2007 |
$103,000,000 |
Prop I |
High School #2 ($98,800,000) |
1,809 |
2,079 |
3,888 |
Defeated |
| Prop II |
Agricultural Science Facility ($2,500,000) |
2,165 |
1,737 |
3,902 |
Passed |
| Prop III |
Land Purchases ($1,700,000) |
1,916 |
1,954 |
3,870 |
Defeated |
| November
7, 2006 |
$15,700,000 |
Prop I |
Agricultural
Science Facility; New Field House at Don Floyd; Competition softball and
base field at Don Floyd site;Upgrades to DF fields; Band Instruments; Land;
Upgrades to WGMS athletic field |
2,059 |
2,241 |
4,300 |
Defeated |
| May
13, 2006 |
$70,910,000 |
Prop I |
Land Purchase; Construction of LaRue Miller
Elementary #6; Baxter/FSMS Renovations & Additions; Capital Improvements;
Instructional Technology; Buses ($35,270,000) |
1,395 |
1,105 |
2,500 |
Passed |
| Prop II |
Agricultural Science Barn; Land for Ag Barn; HS Band
Instruments & Practice Rooms; HS Athletic Facility Improvements
($12,610,000) |
1,184 |
1,307 |
2,491 |
Defeated |
| Prop III |
Elementary #7; Design of HS #2; Land Purchase
($23,030,000) |
1,176 |
1,305 |
2,481 |
Defeated |
| Feb.
7, 2004 |
$80,015,000 |
Prop I |
High School Renovations ($43,960,000); Walnut Grove
MS #2 phase II (12,570,000); Capital Improvements ($2,990,000); Technology
($1,900,000); Buses ($520,000) |
2,161 |
1,123 |
3,284 |
Passed |
| Prop II |
Multipurpose Stadium ($14,275,000) |
1,741 |
1,520 |
3,261 |
Passed |
| Prop III |
Land Purchases ($3,800,000) |
1,993 |
1,271 |
3,264 |
Passed |
| March 1, 2003 |
$99,535,000 |
Prop I |
New High School 10-12 ($58,590,000); New
Intermediate School ($11,500,000); New Elem. School PK-4 ($10,900,000);
Capital Improvements ($18,545,000) |
701 |
1,559 |
2,260 |
Defeated |
| May 22, 1999 |
$46,425,000 |
Prop I |
Construction of schools; land purchase |
294 |
120 |
414 |
Passed |
| Oct. 21, 1995 |
$24,000,000 |
Prop I |
Construction of schools; land purchase |
687 |
125 |
712 |
Passed |
| May 14, 1983 |
$15,000,000 |
Prop I |
Construction of schools; land purchase |
299 |
181 |
418 |
Passed |
| Sept.
21, 1974 |
|
Prop I |
Tax not to exceed $1.50 per $100 valuation |
438 |
272 |
710 |
Passed |
| $3,000,000 |
Prop II |
Construction of schools; land purchase |
441 |
272 |
713 |
Passed |
| Dec. 11, 1965 |
$100,000 |
Prop I |
Construction of schools; land purchase |
135 |
50 |
185 |
Passed |
| June 30, 1962 |
$195,000 |
Prop I |
Construction of schools; land purchase |
261 |
45 |
306 |
Passed |
| May
24, 1958 |
|
Prop I |
Tax not to exceed $1.50 per $100 valuation |
112 |
59 |
171 |
Passed |
| $110,000 |
Prop II |
Construction of schools; land purchase |
80 |
79 |
159 |
Passed |
| |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
| |
|
| |
| |
| Top |
| |
|
|
 |
 |
 |
| |
|
|
|
|